The Infona portal uses cookies, i.e. strings of text saved by a browser on the user's device. The portal can access those files and use them to remember the user's data, such as their chosen settings (screen view, interface language, etc.), or their login data. By using the Infona portal the user accepts automatic saving and using this information for portal operation purposes. More information on the subject can be found in the Privacy Policy and Terms of Service. By closing this window the user confirms that they have read the information on cookie usage, and they accept the privacy policy and the way cookies are used by the portal. You can change the cookie settings in your browser.
With obvious economic and social benefits, four-parallel lines on the same tower is widely used and has high reliability requirements, the use of live working to carry out maintenance is particularly important. This paper takes 500/220kV four-parallel lines on the same tower as the research object. First, through the analysis of the risk of 500kV and 220kV line typical operation position, it can be...
The multi-circuit transmission lines on the same tower can be considered for solving the contradiction between the growing electricity demand and the limited line corridor. Take the 500kV/220kV four-circuit mixed-voltage transmission lines as an example, the maintenance circuit would have high induced voltage and induced current because of the strong electrostatic coupling and electromagnetic coupling...
Once the UHV transmission lines were put into operation, it is hard to repair at outage. The live working is the forceful guarantee for the security and stability of operation of the UHV transmission lines. The length of the UHV strain insulator string achieves about 12.5 m and the distance between the adjacent strings achieves about 1.0 m. As entering the strong electric field along the UHV strain...
The 500k V double-circuit lines on same tower has some advantages such as small line corridors and large capability, electric field for live-working becomes more complicated because of its compact triple conductors. In this paper, the compact tower is took as the research object, the field strength on body surface at some typical positions during the live working are calculated using finite element...
Most live working projects need lineman enter Equal Potential Working(EPW) for handling, so which method to enter EPW has a significant impact on safety of the lineman. With 220kV cup type tower as objects, the simulation model of the lineman use insulating ladder and hanging basket to enter EPW is established, and filed intensity on body surface is calculated based on finite element method. Simulation...
The large capacity, long distance, high efficiency transmission electric energy can be realized by the UHV DC transmission technology, which can promote energy structure adjustment and optimized layout. Live working is the powerful guarantee for the safe and stable operation of the UHV DC transmission lines. Take the straight-line tower as an example, simulation models of entering the electric field...
Set the date range to filter the displayed results. You can set a starting date, ending date or both. You can enter the dates manually or choose them from the calendar.